The Artemis is a DP-1 Anchor Handling Tug & Supply Vessel, built in Husum, Germany in 1984. She was acquired by the Asso Group in 2013, fully overhauled and upgraded in Chalkis Shipyards in Greece in 2014 (including Transfer of Class to ABS) and now operates mainly as a support vessel for the Group’s CLV Atalanti on a worldwide basis offering, in addition, extensive supply, stand-by and auxiliary services on the various projects that she is involved in.
When not involved in support operations for the Group, she is employed on various offshore and subsea scopes of work including ROV operations, surveys, etc. On occasion, she is also chartered out as a pure towing vessel given her high Bollard Pull figures.
She holds a long track record on a variety of offshore projects and is being kept up to date with new equipment and careful maintenance to ensure zero down-time and highest possible performance on her employments.
The Artemis (/ˈɑːrtɪmɪs/; in Greek: Άρτεμις) is named after the Greek mythological goddess of the hunt, the wilderness, wild animals, the Moon and chastity. She was the daughter of Zeus and Leto, and the twin sister of Apollo. The goddess Diana is her Roman equivalent.
Kaskasi II (Germany) – Subsea Cable Laying & Protection
The Kaskasi II project concerns the realization of a three-phase AC connection in North-Sea-Cluster 4. The three-phase current generated in the Kaskasi II offshore wind farm is to be transported to the HVDC substation HelWin Beta via two AC subma …
Viking Link is a 1,400MW 760km subsea interconnector between the substation Bicker Fen in Lincolnshire, UK and the substation Revsing in southern Jutland, Denmark. The purpose of the project is the transmission of electrical energy between Revsing Den …
The Kafireas project concerns the interconnection of 16 Wind Farms located at the southern part of Evia Island (southeast of Karystos) to the Hellenic mainland Power Grid at Pallini EHV Center (Attica region). The interconnection will be configured by …
The IFA2 project concerns the HVDC and HVAC electricity transmission interconnector between France and England across the English Channel. In addition to the main HVDC interconnection, there is a HVAC link from the converter station at the main English …
The “Albatros” project concerns the HVAC grid connection to the offshore wind farm Albatros. The connection uses the existing “north” Global Tech 1 cable route (Borwin beta – GlobalTech 1) already installed. After the initial pull-in at Albatros OWF pl …
Deutsche Bucht – Submarine Link Cables Installation and Protection
The DBU project concerns the HVAC submarine link between the AC/DC offshore converter station BorWin beta platform and the Deutsche Bucht offshore wind park, located in the South-West German Bight region of the southern North Sea. The system is compose …
Global Tech 1 – Submarine Link Cables Installation and Protection
The Global Tech 1 (GT-1) project concerns the realization of a new HVAC grid connection between the offshore substation BorWin Gamma and the grid connection point (OSS) on the OWF Global Tech 1 by jointing the existing cables and new cables. The system …
The Rampion Offshore Wind Farm (ROWF) is located in the English Channel, approximately 13km offshore the Sussex coast. The wind farm consists of 116 wind turbines, installed at water depths between 19m and 40m. The maximum total output is 400MW and the …
The COBRA cable project consists of the power link between Denmark and The Netherlands and it has been developed by Energinet.dk and TenneT TSO B.V. The purpose of COBRA Cable is to allow for the integration of more renewable energy into the Dutch and …
BorWin3 project refers to a 900MW DC grid connection system in the North Sea cluster 8 developed by TenneT. The system’s direct current is transmitted from BorWin gamma offshore converter platform to a TenneT substation located in Emden/Ost, through a …
The COBRA cable project consists of the power link between Denmark and The Netherlands and it has been developed by Energinet.dk and TenneT TSO B.V. The cables system that was installed is composed by: 2 High Voltage Direct Current (HVDC) 1 Fiber …
Global Tech 1 – Submarine Link Cables Installation and Protection
The Global Tech 1 (GT-1) project concerns the realization of a new HVAC grid connection between the offshore substation BorWin Gamma and the grid connection point (OSS) on the OWF Global Tech 1 by jointing the existing cables and new cables. The system …
The Rampion Offshore Wind Farm (ROWF) is located in the English Channel, approximately 13km offshore the Sussex coast. The wind farm consists of 116 wind turbines, installed at water depths between 19m and 40m. The maximum total output is 400MW and the …
The COBRA cable project consists of the power link between Denmark and The Netherlands and it has been developed by Energinet.dk and TenneT TSO B.V. The purpose of COBRA Cable is to allow for the integration of more renewable energy into the Dutch and …
BorWin3 project refers to a 900MW DC grid connection system in the North Sea cluster 8 developed by TenneT. The system’s direct current is transmitted from BorWin gamma offshore converter platform to a TenneT substation located in Emden/Ost, through a …
The COBRA cable project consists of the power link between Denmark and The Netherlands and it has been developed by Energinet.dk and TenneT TSO B.V. The cables system that was installed is composed by: 2 High Voltage Direct Current (HVDC) 1 Fiber …
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behavior or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional
Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes.The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.